Solomon High Voltage Operations Work

The Solomon High Voltage Team has been working hand in hand with FMG in the successful commissioning and energisation of Solomon Mine. including the 120 MW Power station, 132 kV Network, Train Load Out, Stockyard, Kangi Village and both the Firetail and Kings Valley Ore Processing Facilities with over 300 high voltage initial energisations executed incident free to date.

The HVO team has been instrumental in reaching FMG commissioning targets by providing streamlined permitting, isolation and high voltage access solutions across the entire Solomon high voltage network and has assisted in implementing procedures, HV training and familiarisation of construction and commissioning personnel across site.

Incoming overhead power lines in outback